  • The burnup chart app is designed to track estimated time of project completion. Now, at any moment, you can view estimated time when a project will be completed, if you have appropriate access permissions for this project. The app itself is launched inside a workgroup.

    The burnup chart app displays project completion chart, arranged based on a number of tasks at a specified time. If you didn't select a project or selected a project without any tasks, you will see the “overview” chart with demo data.

    Chart elements

    ●     X-direction: calendar period that shows how many “Tasks” were completed or will be completed within specified time.

    ●     X-direction: 2 lines in different colors are displayed to show estimated time for project completion.

    ○     Green line – shows time when the project will be completed faster than an average project completion time.

    ○     Red line - shows time when the project will be completed slower than an average project completion time.

    ●     Y-direction: indicates the number of tasks that were completed or will be completed within a calendar period, specified in “Date”.

    ●     X- and Y- directions: show provisional graduation lines, allowing to visually split the completion of tasks into time segments.

    ●     Three sectors go through the complete chart. Designations for these sectors can be found in the list of chart symbols.

    Additional app elements

    ●     The “Today” date

    ●     The “Refresh” button that updates the chart.

    ●     The “Task completed” diagram shows how many tasks were completed in total and which number of tasks are still yet to be done.

    ○     Done – completed tasks

    ○     Undone – tasks in progress.

    ●      The “Task deadline” diagram shows how many tasks are completed relative to deadline.

    ○     Best – shows tasks, completed before a deadline

    ○     Worst - shows tasks, completed after a deadline.

    ●     List of symbols used to designate the chart data.

    How we calculate end of the project.

    Formula: (scope / (scope + median)) * project_interval.

    ●     Scope - total number of tasks,

    ●     Median - median deviation from the plan,

    ●     Project_interval - the interval of the project: from start to deadline.

    Attention! The new version of the app works as a 30-day trial on free Bitrix24 accounts. After upgrading the previous versions, you will need to authorize the application for the second time.

  • Version 2
    We have optimized the data upload process for projects with large number of tasks.
    Attention! The new version of the app works as a 30-day trial on free Bitrix24 accounts. After upgrading the previous versions, you will need to authorize the application for the second time.

    Version 1
    Now, at any moment, you can view a tentative time when a project will be completed.